Project Go-Live Readiness Decision Governance

Standards

Project Go-Live Readiness Decision Governance
Number 
121.10 Now PM-01-01-S
Policy Action Date
Adopted July 19, 2023
Purpose 

The decision to go-live with a new IT solution is one of the most important decisions a project Steering Committee and Executive Sponsor must make.  The decision must consider the readiness of not only the solution, but also the organization(s) responsible for supporting the solution and those required to use it.  The decision should be informed by several sources and types of data, and may even require a discussion with the OCIO.

This policy outlines the minimum expectations for any IT investment determined to be “major” or “under OCIO project oversight”.